Some aspects of planning for Southeastern Massachusetts Technological Institute: Report to the Commonwealth of Massachusetts executive Office for Administration and Finance, Central Services Division, Bureau of Building Construction, by Arthur D. Little Inc., June 1963
File — Box: 1A
Identifier: URC 60, series I
Dates:
June 1963
Student Center and Dormitories: Stage 1. Feasibility Study and Recommendations developed for The Building Authority of Southeastern Massachusetts Technological Institute. by Campus Facilities Associates, August 1966
File — Box: 1A
Identifier: URC 60, series I
Dates:
August 1966
Southeastern Massachusetts University Academic Building Study, Massachusetts State Project E 69-4, by Brigham, Eldredge, Limon and Hussey Architects, May 12, 1972
File — Box: 1A
Identifier: URC 60, series I
Dates:
May 12, 1972
Site work specifications, 1964
File — Box: 1A
Identifier: URC 60, series II, sub-series 1
Dates:
1964
Found in:
Claire T. Carney Library Archives and Special Collections, University of Massachusetts Dartmouth
/
URC -060, UMass Dartmouth, Office of Campus Master Planning & Facilities Management records
/
Series II: Construction, repair & maintenance contracts & documents
/
Sub-series 1: Site work and preparation
Sewage holding system, SMTI, 1966
File — Box: 1A
Identifier: URC 60, series II, sub-series 1
Dates:
1966
Found in:
Claire T. Carney Library Archives and Special Collections, University of Massachusetts Dartmouth
/
URC -060, UMass Dartmouth, Office of Campus Master Planning & Facilities Management records
/
Series II: Construction, repair & maintenance contracts & documents
/
Sub-series 1: Site work and preparation
Expansion of campus utilities, 1967
File — Box: 1A
Identifier: URC 60, series II, sub-series 1
Dates:
1967
Found in:
Claire T. Carney Library Archives and Special Collections, University of Massachusetts Dartmouth
/
URC -060, UMass Dartmouth, Office of Campus Master Planning & Facilities Management records
/
Series II: Construction, repair & maintenance contracts & documents
/
Sub-series 1: Site work and preparation
Project and contract code list, 1965 - 1984
File — Box: 1A
Identifier: URC 60, series I
Dates:
1965 - 1984
Architecture of campus - articles, 1967 - 1975
File — Box: 1A
Identifier: URC 60, series I
Dates:
1967 - 1975
Addendum to Feasibility Study for a proposed new student residence at Southeastern Massachusetts University, by Ondras Associates, March 1985
File — Box: 1A
Identifier: URC 60, series I
Dates:
March 1985