Box 3
Container
Contains 29 Results:
North girder span 15, Somerset/Fall River Bridge, no. 58, 1963-08-06
Item — Box: 3
Identifier: PC2. 163
Scope and Contents
From the Collection:
The collection consists of 175 photoprints detailing the progress of the construction of Interstate 195’s bridges and interchanges in the Fall River area, with the majority being construction of the bridge between Fall River and Somerset, Massachusetts, over the Taunton River. There are four contracts documented, each group originally housed in a separate binder. Each photograph is labelled and numbered by either the photographer or the contractor, the sequence of which is not always clear...
Dates:
1963-08-06
Found in:
Claire T. Carney Library Archives and Special Collections, University of Massachusetts Dartmouth
/
PC-002, Interstate 195 construction progress photographs
/
Series I: Somerset/Fall River [Taunton River] bridge construction photographs
/
Sub-Series II: Contract # 9073 (Contractor: American Bridge, Division of United States Steel)
Strut erecting truss P.P.33, Somerset/Fall River Bridge, no. 59, 1963-08-06
Item — Box: 3
Identifier: PC2. 164
Scope and Contents
From the Collection:
The collection consists of 175 photoprints detailing the progress of the construction of Interstate 195’s bridges and interchanges in the Fall River area, with the majority being construction of the bridge between Fall River and Somerset, Massachusetts, over the Taunton River. There are four contracts documented, each group originally housed in a separate binder. Each photograph is labelled and numbered by either the photographer or the contractor, the sequence of which is not always clear...
Dates:
1963-08-06
Found in:
Claire T. Carney Library Archives and Special Collections, University of Massachusetts Dartmouth
/
PC-002, Interstate 195 construction progress photographs
/
Series I: Somerset/Fall River [Taunton River] bridge construction photographs
/
Sub-Series II: Contract # 9073 (Contractor: American Bridge, Division of United States Steel)
West approach and truss, Somerset/Fall River Bridge, no. 60, 1963-10-04
Item — Box: 3
Identifier: PC2. 165
Scope and Contents
From the Collection:
The collection consists of 175 photoprints detailing the progress of the construction of Interstate 195’s bridges and interchanges in the Fall River area, with the majority being construction of the bridge between Fall River and Somerset, Massachusetts, over the Taunton River. There are four contracts documented, each group originally housed in a separate binder. Each photograph is labelled and numbered by either the photographer or the contractor, the sequence of which is not always clear...
Dates:
1963-10-04
Found in:
Claire T. Carney Library Archives and Special Collections, University of Massachusetts Dartmouth
/
PC-002, Interstate 195 construction progress photographs
/
Series I: Somerset/Fall River [Taunton River] bridge construction photographs
/
Sub-Series II: Contract # 9073 (Contractor: American Bridge, Division of United States Steel)
East anchor-truss span, Somerset/Fall River Bridge, no. 61, 1963-10-04
Item — Box: 3
Identifier: PC2. 166
Scope and Contents
From the Collection:
The collection consists of 175 photoprints detailing the progress of the construction of Interstate 195’s bridges and interchanges in the Fall River area, with the majority being construction of the bridge between Fall River and Somerset, Massachusetts, over the Taunton River. There are four contracts documented, each group originally housed in a separate binder. Each photograph is labelled and numbered by either the photographer or the contractor, the sequence of which is not always clear...
Dates:
1963-10-04
Found in:
Claire T. Carney Library Archives and Special Collections, University of Massachusetts Dartmouth
/
PC-002, Interstate 195 construction progress photographs
/
Series I: Somerset/Fall River [Taunton River] bridge construction photographs
/
Sub-Series II: Contract # 9073 (Contractor: American Bridge, Division of United States Steel)
East approach and truss looking north, Somerset/Fall River Bridge, no. 62, 1963-10-14
Item — Box: 3
Identifier: PC2. 167
Scope and Contents
From the Collection:
The collection consists of 175 photoprints detailing the progress of the construction of Interstate 195’s bridges and interchanges in the Fall River area, with the majority being construction of the bridge between Fall River and Somerset, Massachusetts, over the Taunton River. There are four contracts documented, each group originally housed in a separate binder. Each photograph is labelled and numbered by either the photographer or the contractor, the sequence of which is not always clear...
Dates:
1963-10-14
Found in:
Claire T. Carney Library Archives and Special Collections, University of Massachusetts Dartmouth
/
PC-002, Interstate 195 construction progress photographs
/
Series I: Somerset/Fall River [Taunton River] bridge construction photographs
/
Sub-Series II: Contract # 9073 (Contractor: American Bridge, Division of United States Steel)
West approach looking north, Somerset/Fall River Bridge, no. 63, 1963-10-14
Item — Box: 3
Identifier: PC2. 168
Scope and Contents
From the Collection:
The collection consists of 175 photoprints detailing the progress of the construction of Interstate 195’s bridges and interchanges in the Fall River area, with the majority being construction of the bridge between Fall River and Somerset, Massachusetts, over the Taunton River. There are four contracts documented, each group originally housed in a separate binder. Each photograph is labelled and numbered by either the photographer or the contractor, the sequence of which is not always clear...
Dates:
1963-10-14
Found in:
Claire T. Carney Library Archives and Special Collections, University of Massachusetts Dartmouth
/
PC-002, Interstate 195 construction progress photographs
/
Series I: Somerset/Fall River [Taunton River] bridge construction photographs
/
Sub-Series II: Contract # 9073 (Contractor: American Bridge, Division of United States Steel)
East anchor truss & approach from Pier 17, Somerset/Fall River Bridge, no. 64, 1963-12-04
Item — Box: 3
Identifier: PC2. 169
Scope and Contents
From the Collection:
The collection consists of 175 photoprints detailing the progress of the construction of Interstate 195’s bridges and interchanges in the Fall River area, with the majority being construction of the bridge between Fall River and Somerset, Massachusetts, over the Taunton River. There are four contracts documented, each group originally housed in a separate binder. Each photograph is labelled and numbered by either the photographer or the contractor, the sequence of which is not always clear...
Dates:
1963-12-04
Found in:
Claire T. Carney Library Archives and Special Collections, University of Massachusetts Dartmouth
/
PC-002, Interstate 195 construction progress photographs
/
Series I: Somerset/Fall River [Taunton River] bridge construction photographs
/
Sub-Series II: Contract # 9073 (Contractor: American Bridge, Division of United States Steel)
Pinning top plate at U23A, Somerset/Fall River Bridge, no. 65, 1963-12-04
Item — Box: 3
Identifier: PC2. 170
Scope and Contents
From the Collection:
The collection consists of 175 photoprints detailing the progress of the construction of Interstate 195’s bridges and interchanges in the Fall River area, with the majority being construction of the bridge between Fall River and Somerset, Massachusetts, over the Taunton River. There are four contracts documented, each group originally housed in a separate binder. Each photograph is labelled and numbered by either the photographer or the contractor, the sequence of which is not always clear...
Dates:
1963-12-04
Found in:
Claire T. Carney Library Archives and Special Collections, University of Massachusetts Dartmouth
/
PC-002, Interstate 195 construction progress photographs
/
Series I: Somerset/Fall River [Taunton River] bridge construction photographs
/
Sub-Series II: Contract # 9073 (Contractor: American Bridge, Division of United States Steel)
"B" truss P.P 31--30, 1963-12-04
Item — Box: 3
Identifier: PC2. 171
Scope and Contents
From the Collection:
The collection consists of 175 photoprints detailing the progress of the construction of Interstate 195’s bridges and interchanges in the Fall River area, with the majority being construction of the bridge between Fall River and Somerset, Massachusetts, over the Taunton River. There are four contracts documented, each group originally housed in a separate binder. Each photograph is labelled and numbered by either the photographer or the contractor, the sequence of which is not always clear...
Dates:
1963-12-04
Found in:
Claire T. Carney Library Archives and Special Collections, University of Massachusetts Dartmouth
/
PC-002, Interstate 195 construction progress photographs
/
Series I: Somerset/Fall River [Taunton River] bridge construction photographs
/
Sub-Series II: Contract # 9073 (Contractor: American Bridge, Division of United States Steel)
Pinning gusset plate for PP. L, Somerset/Fall River Bridge, no. 67, 1963-12-04
Item — Box: 3
Identifier: PC2. 172
Scope and Contents
From the Collection:
The collection consists of 175 photoprints detailing the progress of the construction of Interstate 195’s bridges and interchanges in the Fall River area, with the majority being construction of the bridge between Fall River and Somerset, Massachusetts, over the Taunton River. There are four contracts documented, each group originally housed in a separate binder. Each photograph is labelled and numbered by either the photographer or the contractor, the sequence of which is not always clear...
Dates:
1963-12-04
Found in:
Claire T. Carney Library Archives and Special Collections, University of Massachusetts Dartmouth
/
PC-002, Interstate 195 construction progress photographs
/
Series I: Somerset/Fall River [Taunton River] bridge construction photographs
/
Sub-Series II: Contract # 9073 (Contractor: American Bridge, Division of United States Steel)